At December 31, 2018, the Company was contingently liable in the amount of approximately $537.0 million in issued standby letters of credit and $5.6 billion in issued surety bonds primarily to support project execution.

 

In the ordinary course of business, the Company enters into various agreements providing financial or performance assurances to clients on behalf of certain unconsolidated partnerships, joint ventures and other jointly executed contracts. These agreements are entered into primarily to support the project execution commitments of these entities.

 

In addition, in connection with the investment activities of AECOM Capital, the Company provides guarantees of contractual obligations, including guarantees for completion of projects, repayment of debt, environmental indemnity obligations and other lender required guarantees.

 

The Company’s investment adviser jointly manages, sponsors and owns equity interest in the AECOM-Canyon Equity Fund, L.P. (the “Fund”), in which the Company has an ongoing capital commitment to fund investments. At December 31, 2018, the Company has capital commitments of $35 million to the Fund over the next 10 years.

 

DOE Deactivation, Demolition, and Removal Project

 

Washington Group International, an Ohio company (WGI Ohio), an affiliate of URS, executed a cost-reimbursable task order with the Department of Energy (DOE) in 2007 to provide deactivation, demolition and removal services at a New York State project site that, during 2010, experienced contamination and performance issues and remains uncompleted. In February 2011, WGI Ohio and the DOE executed a Task Order Modification that changed some cost-reimbursable contract provisions to at-risk. The Task Order Modification, including subsequent amendments, requires the DOE to pay all project costs up to $106 million, requires WGI Ohio and the DOE to equally share in all project costs incurred from $106 million to $146 million, and requires WGI Ohio to pay all project costs exceeding $146 million.

 

Due to unanticipated requirements and permitting delays by federal and state agencies, as well as delays and related ground stabilization activities caused by Hurricane Irene in 2011, WGI Ohio has been required to perform work outside the scope of the Task Order Modification. In December 2014, WGI Ohio submitted claims against the DOE pursuant to the Contracts Disputes Acts seeking recovery of $103 million, including additional fees on changed work scope. WGI Ohio has incurred and continues to incur additional project costs outside the scope of the contract as a result of differing site and ground conditions and intends to submit additional formal claims against the DOE.

 

Due to significant delays and uncertainties about responsibilities for the scope of remaining work, final project completion costs and other associated costs have exceeded $100 million over the contracted and claimed amounts. WGI Ohio assets and liabilities, including the value of the above costs and claims, were measured at their fair value on October 17, 2014, the date AECOM acquired WGI Ohio’s parent company, which measurement has been reevaluated to account for developments pertaining to this matter. Deconstruction and decommissioning activities are completed and site restoration activities are underway. WGI Ohio increased its receivable during the quarter ended June 30, 2018.

 

WGI Ohio can provide no certainty that it will recover the claims submitted against DOE in December 2014, any future claims or any other project costs after December 2014 that WGI Ohio may be obligated to incur including the remaining project completion costs, which could have a material adverse effect on the Company’s results of operations.

 

SR-91

 

One of the Company’s wholly-owned subsidiaries, URS Corporation, entered into a partial fixed cost and partial time and material design agreement in 2012 with a design build contractor for a state route highway construction project in Riverside County and Orange County, California. On April 1, 2017, URS Corporation filed an $8.2 million amended complaint in the Superior Court of California against the design build contractor for its failure to pay for services performed under the design agreement. On July 3, 2017, the design build contractor filed an amended cross-complaint against URS Corporation and AECOM in Superior Court alleging breaches of contract, negligent interference and professional negligence pertaining to URS Corporation’s performance of design services under the design agreement, seeking purported damages of $70 million. On May 4, 2018, the design build contractor dismissed its claims for negligent interference. On May 24, 2018, URS Corporation filed an $11.9 million second amended complaint in Superior Court against the design build contractor for its failure to pay for services performed under the design agreement. URS Corporation and AECOM cannot provide assurances that URS Corporation will be successful in the recovery of the amounts owed to it under the design agreement or in their defense against the amounts alleged under the cross-complaint that they believe are without merit and that they intend to vigorously defend against. The potential range of loss in excess of any current accrual cannot be reasonably estimated at this time primarily because the matter involves complex factual and legal issues; there is substantial uncertainty regarding any alleged damages, including due to liability of and payments, by third parties; and the matter is at a discovery stage of litigation.

 